Project: RANS21RB   -  
            Listing of Entries
    (Please mouse-over any icon to get a description of that function).



Categories
  
Builder Name:Randall Brooks   -  
Project:   Rans - S-21 Outbound   -   VIEW REPORTS
Total Hours:1990
Total Flight Time:
Start/Last Date:Apr 03, 2021 - No Finish Date
Engine:Titan IO-340 180HP
Propeller:Whirlwind
 
Friendly URL: https://eaabuilderslog.org?s=RANS21RB

Home or Last Project Picture

Apr 26, 2023     Fairings and wingtips - (5 hours)       Category: Fuselage
Fabricated Horizontal stab to fuselage fairing. Match drilled and drilled for #6 nutplates in stab. Fabricated wing strut fairing. Cut out for strut profile. Drilled and installed nutplates in bottom fuselage inspection plate for tailwheel cable covers. Temp installed wing tip rib to align aileron and set flap trailing edge to match aileron. Fit flap gap seal. Will wait to install when skylight is installed.


 


NOTE: This information is strictly used for the EAA Builders Log project within the EAA organization.     -     Policy     -     © Copyright 2024 Brevard Web Pro, Inc.